Energy Audit ALSTOM Bexbach

Site:

Alstom Power Systems GmbH
66450 Bexbach
Germany
http://www.de.alstom.com

Power Systems - Schaufelfertigung
Das Werk Bexbach (Saarland) der Alstom Power Systems GmbH Mannheim gehört weltweit zu den modernsten Anlagen zur Fertigung von Turbinenschaufeln.
Im Werk Bexbach arbeiten rund 240 Mitarbeiterinnen und Mitarbeiter.

Produktionsprogramm
Dampfturbinen-Leitschaufeln
Verdichter-Leitsschaufeln
Gasturbinen-Leitschaufeln
Gasturbinen-Laufschaufeln

Offices and production’s surface    92752 m2

The site:
The site of Bexbach is dedicated to the engineering of blades for power plant turbines.The industrial activity of the site of Bexbach includes:

−    The manufacturing of blades for power plant turbines of all sizes
−    Training of service technicians
−    Single-part production and repair of blades

At September 2008 the manpower of the buildings was about 248 employees.

The Energy Audit contains the following

Production of audit report and action plan:

• a picture of energy consumption on site (including electricity, natural
gas and water) and its breakdown
• an assessment of the performance of the major energy consuming
items: compressed air, steam, cold production, ventilation, heating and
air-conditioning, lighting, process consumption
• Recommendations for improving the energy metering plan
• Assessment and prioritization of each proposed improvement (investment, running cost)
• Reporting language is English

The methodology for the study consists in the following steps:
• Preparation of standardized questionnaire for each building
• Site visit, including potential data logging according to the results of the document analysis
• Production of a report clearly and simply summarizing diagnostics and proposed action plan

Process organization:
ECOBAU CONSULTING works as a subcontractor to Bureau Veritas.

Timeline:
For the Bexbach site (3 buildings, 8.507 m2 )
Submission of report and closing meeting: 4 weeks after final inspection on site.
For the Manheim site ( 21 buildings, 87.740 m2)
Submission of report and closing meeting: 6 weeks after final inspection on site.

Auftraggeber:

Bureau Veritas
Industry Services GmbH
Hoheloogstraße 14
67065 Ludwigshafen
Germany
http://www.bureauveritas.de


TGA Analysen:

IBW - INGENIEURBÜRO DIPL.- ING. WELF WEINSTOCK
TECHNISCHE GEBÄUDEAUSRÜSTUNG
TEL.:   +49(30) 31 98 11 99 - 19
FAX:    +49(30) 711 03 71
FUNK:   +49(173) 219 33 00
MAIL:   carsten.meyer@ing-ibw.de
http://www.ing-ibw.de

BÜRO: 9-12.00h 14-17.30h TEL: 0049 (0) 30 / 41716840 FAX: -45  | E-MAIL:office(at)ecobauconsulting.de